Monday 28th January
As told in the meeting a week ago, we received a schedule for the whole development, filming and post process. This process would give us 2-3 weeks to complete all audio post production for the film. In the previous meeting, we had asked if we could receive a picture lock at least 2 weeks before the final deadline for us to complete the post production to the highest standard possible.
Week 1 |
14th Jan – 20th Jan |
• Roles confirmed• Idea Finalised• Research into both roles and area of subject• Create digital logo for Ellipsis Productions |
Week 2 |
21st Jan – 27th Jan |
• Script Development• Multiple Platforms (website, facebook) to be created• Proposal Completed |
Week 3 |
28th Jan – 3rd Feb |
• First Draft of script to be completed |
Week 4 |
4th Feb – 10th Feb |
• Location scouting and Actor auditions • Gathering of any props |
Week 5 |
11th Feb – 17th Feb |
• |
Week 6 |
18th Feb – 24th Feb |
• Mon & Wed Filming |
Week 7 |
25th Feb – 3rd March |
• Filming |
Week 8 |
4th March – 10th March |
• Filming• Footage uploaded |
Week 9 |
11th March – 17th March |
• Film/Edit |
Week 10 |
18th March – 24th March |
• Edit |
Easter |
25th March – 31st March |
• |
Easter |
1st April – 7th April |
• Edit |
Easter |
8th April – 14th April |
• Edit |
Easter |
15th April – 21st April |
• Edit |
Week 11 |
22nd April – 28th April |
• Edit |
Week 12 |
29th April – 5th May |
• Final piece to be burnt onto disks• Paper work finalised |
HAND IN |
MAY 8TH |
• Hand word in |